Hypermarket with an underground parking, an underground tank for fire-fighting needs, an underground tank for irrigation needs, a decorative navigation tower and retaining walls along the borders of the Regulated Land Plot
Completion stage Act 16
New developed area 9030 sq. m
Implementation period: from 19.02.2024 to 07.12.2024
* There are no photos and explanations due to the confidentiality policy of the contracting company.
KAMMARTON - warehouses, offices and Fire tank in Regulated Land Plot I - 233, / land property with an identifier 68134.4355.233/, quarter 6, locality "Warehouse and production area Modern suburb - Obelya", municipality of Sofia- district "Lyulin"
Completion stage Act 16
New developed area 12 370.69 sq. m
Implementation period: from 15.11.2023 to 13.10.2024
Reconstruction and enlargement of logistics center, Ravno Pole, Stage 1, 2, 3 & 4
Completion stage Act 16
New developed area 26 613 sq. m
Implementation period: from 04.01.2021 to 15.04.2024
* There are no photos and explanations due to the confidentiality policy of the contracting company.
Residential buildings with underground garages in Regulated Land Plot IV-751, 1970, 1973, 1971, 1972, 2184, 1975, 2185, 1978, quarter 112, "Krastova vada", district Triaditsa, city of Sofia - STAGE 1, 2, 3 - part of "Vitosha View" with a total area of 26 354 sq. m
Stage 1 - Building 4
Stage 2- Building 1 with bistro, children's corner, indoor pool, underground garages and parking spaces
Stage 3 - Building 2 with underground garages and parking spaces
New developed area: Building 4 - 4 965 sq. m,
New developed area: Building 1 - 2 990 sq. m,
New developed area: Building 2 - 1 000 sq. m
Building 4 - Completion stage Act 15
Building 1, 2, 3 - Completion stage Act 14
Implementation period for Stage1: from 15.09.2022 to 18.04.2024
Implementation period for Stage2 and Stage 3: from 06.05.2023 to 31.10.2023